Gas Pipeline Project: NNPCL Not Responsible For Delay – Contractor
One of the contractors for the Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline Project, Brentex CPP Limited (BCL), has refuted media reports blaming the Nigerian National Petroleum Company Ltd (NNPCL) for the project’s delay.
The company affirmed that it has received substantial support from NNPCL in delivering its AKK Gas Pipeline Project segment.
Brentex issued this clarification following its appearance at a Tuesday hearing at the Senate Committee on Local Content, chaired by Senator Natasha Akpoti-Uduaghan.
Some media reports claimed that Sani Abubakar, chairman of Brentex CPP Limited, informed the committee of NNPCL’s attempts to descope the contract’s $1.27 billion station component.
However, in a statement yesterday, Brentex absolved NNPCL of any wrongdoing mentioned in those reports. The company clarified that the committee had requested BCL to confirm its commitment to deliver its project segment (318 km x 40″ Segment 2) by the first quarter of 2025.
READ ALSO: RNDA Threatens Showdown over NNPCL’s ‘Secret Award of $Multi-Billion Pipeline Contract’
Brentex responded that it has completed over 80% of the pipeline construction work, including crossings.
The company added that it is collaborating with NNPCL to deliver all the stations by the first quarter of 2025, except for two Terminal Gas Stations (TGS), which are currently under descope discussions between NNPCL and BCL.
The company also clarified that the $1.27 billion mentioned in some reports pertains to the entire value of the Engineering, Procurement, and Construction (EPC) Segment 2 contract, not the value of the two TGS.
It also said the two TGS stations represent only about 10% of the contract value.
The statement said, “We are one of the two contractors, and there are two segments of the project. BCL is only the contractor for segment 2 of the AKK project-Sarkin Pawa in Niger State to Tamburawa in Kano State.
“For the purpose of emphasis, BCL wishes to add that it is very proud with the progress of its work.
“The company said that any check will confirm that BCL’s performance is easily the best in the history of government-funded pipeline construction projects in Nigeria.
“Furthermore, BCL has always recognised the support it receives from the leadership of the NNPCL, without which we may have had no magic to deliver on this project.”
-
World News5 days ago
Biden says ‘nobody can reverse’ his climate agenda. But Trump is poised to try.
-
Business6 days ago
Tinubu Reforms in Nigeria not working, IMF report hints
-
Gist20 hours ago
VIDEO: Congo’s president daughter’s bedroom video leaks
-
Business6 days ago
Nigeria’s Finance Ministry Transfered Over N55m To Personal Account For Perm Sec’s Retirement Party
-
Politics6 days ago
Ondo Decides; Results From Polling Units Trickles In See Live Results Here
-
Politics6 days ago
IMPEACHMENT: Imo Assembly Under Pressure to Remove Gov. Hope
-
News5 days ago
Delta Assembly Approves Name Change for University of Science and Technology, Ozoro
-
News5 days ago
TrackNews Felicitates New NUJ Bayelsa State Exco