Third Mainland Bridge to reopen at midnight

Popoola told the News Agency of Nigeria (NAN) on Sunday in Lagos that the total shutdown had to be lifted because the contractor was able to fasttrack the delicate task they needed to execute.
He said that the initially scheduled 72 hours timeframe was achieved within 48 hours, hence the reopening to traffic 24 hours ahead of schedule.
“We have completed the casting of the three number expansion joints on Third Mainland bridge.
“Therefore, the bridge shall be opened at 12:00 midnight Sunday 27th December and no longer Monday 28th December.
“That is 48 hours and no more 72 hours,” Popoola said.
NAN reports that the controller had on Tuesday, Dec. 22 announced a 72 hours total shutdown of the bridge with effect from midnight on Saturday to midnight Tuesday.
The shutdown was to stop vibrations caused by movement of vehicles for contractors to cast concrete on additional three expansion joints in the ongoing rehabilitation of the bridge.
NAN reports that the Third Mainland Bridge which was going through series of repairs, had to be partially shut on July 24 for another round of rehabilitation works.
READ ALSO: Third Mainland Bridge shut for three days
The repair that was expected to last six months was extended by one month due to the recent #EndSARS protests in Lagos, thereby extending the completion date from January 2021 to February.
The construction was initially divided into two phases of three months on each carriageway, starting with the Oworonsoki bound carriageway whose completion dragged to four months.
Traffic was partially diverted on a stretch of 3.5km where construction is ongoing between Adeniji Adeniji Ramp and Ebute Meta, while different time belts were allotted for traffic diversions on the bridge.
The 11.8km bridge is the longest of the three bridges connecting Lagos Island to the Mainland.
The bridge starts from Oworonshoki, which is linked to the Apapa-Oshodi Expressway and the Lagos-Ibadan Expressway and ends at the Adeniji Adele Interchange on Lagos Island.
Constructed in 1990, the bridge was adjudged as the longest in Africa until 1996 when the Oct. 6 Bridge in Cairo, Egypt was completed.
(NAN)
-
Business3 days ago
An Open Appeal To The Gov. Of Bayelsa State, Sen. Diri Douye Regarding The Removal Of My Prominent Billboard On Azikoro Road, Near Ekeki Park.
-
Politics1 day ago
BREAKING: Wike Faces Another Setback as PDP Rejects Controversial Calabar Congress Report
-
News4 days ago
Police have arrested three suspects who offered a pregnant woman N30 million to terminate her six-month-old fetus for a ritual in Niger State
-
Niger Delta3 days ago
Prophetic Warning: Primate Ayodele Cautions NDDC DG Ogbuku on Imminent Betrayal
-
Gist3 days ago
A housewife in Bauchi has stabbed her husband to death during a dispute over child custody
-
Entertainment1 day ago
‘I’ll Drop Your Son at Your Doorstep’ – Kenyan Woman Calls Out Cubana Chief Priest
-
Politics3 days ago
Tension in Osun: LG Workers Stand Their Ground, Defy APC’s Resumption Order
-
Crime3 days ago
Close Call: Baby Kidnapping Attempt Blocked by Vigilant Residents